Logistics & Supply Chain
Basic

Reorder Point

Stock level that triggers a new order, covering demand during the lead time.

Formula

ROP=dLROP = d L

Live Calculator

Members

Variables

ROPReorder point
dDemand per day
LLead time (days)

Example

d=50/day, L=7: ROP = 350 units

How it works

The reorder point is the inventory level at which you should place a new order so you do not run out before the replacement stock arrives. It works because if you consume d units each day and the supplier needs L days to deliver, you need enough stock to cover d × L units of demand during that waiting period. This basic version assumes demand and lead time are steady and no extra safety stock is included.

When to use it

Use this formula when planning inventory for items that are replenished after a delay, such as retail products, spare parts, or raw materials. It is useful whenever you need to know the exact stock level that should trigger a reorder.

Worked example, step by step

Suppose a warehouse uses 30 boxes per day and the supplier takes 12 days to deliver a new shipment. Given: d = 30 boxes/day, L = 12 days Formula: ROP = d × L Substitute: ROP = 30 × 12 Calculate: ROP = 360 Final answer: reorder when stock falls to 360 boxes

Common mistakes to avoid

  • Using weekly demand with lead time in days without converting the units first
  • Forgetting that this basic formula does not include safety stock for uncertainty
  • Placing the order when inventory reaches zero instead of when it reaches the reorder point

Did You Know?

Set the reorder point too low and you stock out; too high and cash sits frozen on the shelf.